Multipart article

Excel Construction Management Templates

by Diana Ramos on Oct 19, 2015

In this article, you will find a roundup of the top construction Excel templates to help you plan, track, and manage your construction projects from start to finish. We've included brief descriptions of each template to guide you towards the best, most efficient way to use them.

Included on this page, you'll find a construction timeline template, a construction budget template, a construction documentation tracker, a project punchlist template, and many more helpful templates.


Construction Timeline

Construction projects can have multiple phases and numerous tasks that are dependent on each other. If a task is not completed on time, it could delay dependent tasks and result in delayed completion of the entire project. Using a construction project timeline template tracks the progress of your project, allows you to identify risk early and ensures that the project is completed within the time specified in the contract. In this template you can list all of the tasks necessary to complete the project, as well as track the beginning and completion dates, and estimated duration.

Construction Project Timeline Template

 

  Download Excel Template

Try Smartsheet Template  


Transform construction management with Smartsheet. See for yourself.

Construction Safety Dashboard and Build Schedule

Smartsheet enables you to track each project with its own dedicated project sheet and get a unified view across all projects in a dashboard. Monitor tasks across projects and capture on-site issues through a simple form on desktop or mobile.

Watch a free demo

Construction Budget

The construction budget template is helpful for both building and remodeling projects. This template enables you to create a comprehensive construction project budget and ensure that you account for all important items on the list. Additionally, while the construction project is underway, use this spreadsheet as a baseline to track whether you are over or under your budgeted amounts.

  Download Excel Template

Try Smartsheet Template  


Construction Estimator

Depending on the type of construction project, a contractor may need to provide their own estimate for work. This simple construction estimator template will help to provide an initial assessment of the labor and costs associated with a project. Use this template to list the work items needed, along with associated costs, and a total estimate at the bottom.

  Download Excel Template

Try Smartsheet Template  


Bid Tabulation

Depending on the type of construction project, there could be hundreds of bid items that combined make up the final bid amount. Because of this, and the quick turnaround often associated with submitting bids, it is easy to make totalling errors that could significantly alter the final bid amount and affect the decision of who the bid is awarded to. A bid tabulation template is a great tool to verify that the final bid amount is accurately calculated. Additionally, this template includes a column for the owner or engineer’s estimate to compare the initial budgeted amount to each bidder's proposal. 


Bid Tabulation Template

  Download Excel Template
Try Smartsheet Template  


Abstract of Bids

It is often helpful and sometimes even necessary to request bids from multiple contractors or subcontractors for the work you would like completed. Receiving multiple bids will help to ensure you are getting the best price for the work. This abstract of bids template will help you compare all the bids received to make a decision on which contractor to select. By listing each contractor along with their bid amounts and qualifications, you can quickly assess and rank the bids received.


Abstract of Bids Template

  Download Excel Template
Try Smartsheet Template  


Subcontractor Documentation Tracker

Subcontractor Documentation Tracker Template

For construction projects that include subcontractors, keeping track of documentation like contracts, licenses and contact information is important to staying organized. Also, depending on the type of project, collecting and submitting subcontractor documentation may be a requirement and could result in project delays if not submitted in a timely manner. That’s why a subcontractor documentation tracker template is helpful to ensure that you collect all the necessary documentation and keep important details organized. Use this template to track subcontractor information, scope of work and contract details.

 

Download Excel Template
Try Smartsheet Template


Construction Documentation Tracker

Construction projects often require a significant amount of documentation be tracked throughout the project duration. From plans and specifications to inspection reports and weekly progress schedules, keeping these details organized could help expedite the project closeout process. Using a construction documentation tracker template will ensure that you request and receive all required documentation, and enable you to quickly locate items when needed.


Construction Document Tracker Template

Download Excel Template
Try Smartsheet Template


Daily/Weekly Inspection Report

It’s important to regularly check in on the progress of your construction project. Scheduling a weekly project status meeting is helpful, but visiting the job site on a daily or weekly basis is key to visually inspect progress, keep a documented history of the work and identify risk. When making site visits, use this inspection report template to record the amount of hours worked, materials and equipment used and progress made.


Construction Inspection Report Template

Download Excel Template
Try Smartsheet Template


Contractor Progress Payment Template

On projects that extend over a period of time, you will likely pay contractors and subcontractors on a regular schedule, based on the amount of work that is completed during the payment period. This contractor progress payment template helps to determine the payment amount based on the percentage of work completed to date with adjustments made for change orders, previous payments and retainage (if required) for each payment period. Additionally, it includes a second sheet to track the amount of work completed on each task to easily calculate the total completed to date.

 

Contractor Progress Payment Template

Download Excel Template
Try Smartsheet Template


Change Order Request Summary

During a construction project it may be necessary to make changes to the original contracted dollar amount or time-to-completion depending on certain changes like site conditions, scope or unforeseen circumstances. This contractor change order request summary template will allow the contractor to provide a description and breakdown of the requested change, and enable you to make an informed decision on whether the change is necessary and who should be responsible for the impact to the overall project budget and timeline.


Contractor Change Order Template

Download Excel Template
Try Smartsheet Template


Change Order Log

Depending on the length and complexity of the project, it may be necessary to keep track of multiple change order requests over the duration of the project. This change order log template will help to keep track of the change order descriptions, time extensions associated with the changes, and the cumulative contract dollar amount.


Change Order Log Template

Download Excel Template
Try Smartsheet Template


Request for Information Log

Throughout the project, the contractor or subcontractors may have questions regarding the plans or specifications. It is important to have a process in place to collect, review and answer these questions in a timely manner to prevent any delays in work. However you decide to collect the requests for information (RFI), using this template will help to keep the questions and responses organized.Request for Information Template

Download Excel Template
Try Smartsheet Template


Residential Remodel Project Timeline

Work with your team, subcontractors, and clients on your next residential remodel with this project organized in phases. Use the Gantt chart to plan, track status, stay on schedule, and communicate with everyone involved.


Construction Project Timeline Template

Download Excel Template
Try Smartsheet Template


Certified Wage & Hour Payroll Form

Depending on the type of construction project, prime and subcontractors may be required to submit their payroll reports. Although these reports aren’t required on all construction projects, this certified wage and hour payroll template keeps your payroll organized no matter what type of project.


Wage and Hour Report Template

Download Excel Template
Try Smartsheet Template


Time & Materials Invoice

A time and materials invoice is beneficial when emergency or extra work is needed during a project. It enables the contractor and subcontractors to provide quick turnaround on urgent work, while tracking and invoicing for their time and materials. With this time and materials invoice template you can add in the hours spent, materials used and a specific markup amount to calculate the total.


Time and Materials Invoice Template

Download Excel Template
Try Smartsheet Template


Project Punchlist

As construction projects near their completion date, it is important to inspect all the work that was constructed to ensure that it was done per the plans and specifications, and to your standards. This project punchlist template lists and tracks any corrections or updates you would like made, and keeps the contractor and subcontractors on the same page by providing them the complete list. With Smartsheet, the changes are made in real-time so the punchlist is always up to date and can be shared online with multiple subcontractors.


Construction Punchlist Template

Download Excel Template
Try Smartsheet Template


Project Closeout Checklist

Construction project closeout can be a long process due to the many steps that are often required including completion of punchlists, final inspections, contract closeout, submission of as-builts and more. To ensure that each of these steps are completed on time, a project closeout checklist is essential. With this project closeout checklist template, you can list all tasks needing to be completed along with details of each task, specific requirements and the date completed.

Project Closeout Checklist

Download Excel Template
Try Smartsheet Template


Demo of Construction Management in Smartsheet

From pre-construction to project closeout, keep all stakeholders in the loop with real-time collaboration and automated updates so you can make better, more informed decisions, all while landing your projects on time and within budget.

The Smartsheet platform makes it easy to plan, capture, manage, and report on work from anywhere, helping your team be more effective and get more done. Report on key metrics and get real-time visibility into work as it happens with roll-up reports, dashboards, and automated workflows built to keep your team connected and informed.

When teams have clarity into the work getting done, there’s no telling how much more they can accomplish in the same amount of time. Try Smartsheet for free, today.


Frequently Asked Questions

How Do You Calculate or Estimate Construction Costs?

To accurately estimate your construction costs, you must first determine specific aspects of your construction project, like schedule based unit prices, assembly based unit prices, and labor costs. This will give you a baseline understanding of what it will cost you to complete the project.

From there, apply a markup to your costs that will yield profits after any expenses. This will ensure that the project is profitable and comes in under budget. Make sure to track your estimates to ensure that your construction project is hitting under or on budget during every phase of the project.

What Are the Key Steps in Managing a Construction Project?

First, create a comprehensive project plan. Define roles and responsibilities for each phase of the project, and assign specific tasks.

Develop a clear project scope and baselines to assess your project plan for success. Create a schedule for the project and identify cost baselines that should be hit at each part of the project timeline. Analyze project risks and identify specific mitigation plans for any potential risks.

After all of these variables and project details have been established, hold a kickoff meeting to communicate the construction project plan to all involved team members and key stakeholders.

At this time, the procurement phase can begin where the project team obtains all necessary equipment, materials, and resources needed to complete the project.  

The construction phase comes after the planning process and kickoff meeting are complete. The team must get ready for construction by setting up storage facilities, securing the site, and developing a handling and safety plan.

Once construction is complete, the team must commission the project by testing all new systems and equipment, and training personnel to use the updates appropriately. The owner or key stakeholder in the project can then occupy the space and decide whether or not the project meets the expectations that were outlined in the original contract.

The final phase of a construction project is project closeout, where the team completes any outstanding contractual obligations. The team may use a project punch list to identify and complete any tasks that didn’t get completed during the original project. A post-project review outlines all lessons learned and archives any project documents.


Unite construction teams through real-time collaboration with Smartsheet.

Try Smartsheet for Free